Breaking out existing floor slab within restricted hours due to surrounding offices
Excavation of 200m3 of subsoil/aggregate to allow for new floor level
Installation of siphonic drainage system, this system was used as all surrounding sewer lines had a higher invert level
Prepare floor area for slab pour, intallation of dpm, mesh and shutters to box out drainage channel runs
Pour first lower section of floor in one pour
Prepare higher section of floor again installation of dpm, mesh and shutters to retain higher level of concrete
Polish finish higher level of concrete