Templeton Brewery

Works Carried Out

  • Breaking out existing floor slab within restricted hours due to surrounding offices
  • Excavation of 200m3 of subsoil/aggregate to allow for new floor level
  • Installation of siphonic drainage system, this system was used as all surrounding sewer lines had a higher invert level
  • Prepare floor area for slab pour, intallation of dpm, mesh and shutters to box out drainage channel runs
  • Pour first lower section of floor in one pour
  • Prepare higher section of floor again installation of dpm, mesh and shutters to retain higher level of concrete
  • Polish finish higher level of concrete